Green steel trial at the wastewater plant
The plant is only the second city in the country trialing 'green steel' — steel mill slag — to replace ferric chloride for phosphorus removal. Sixty days in, the plant is running better than ever with a third less chemical, and staff built the feeder in-house for $2,150 instead of a $100,000 system.
Illicit railroad storm sewer connection closed
The railroad piped an unpermitted connection into the city storm sewer at Charles and St. James Streets using substandard materials. Staff closed it off; the railroad must go through the engineering department if it wants to reconnect.
Water Utility Fleet and Equipment Needs
The water utility kept three trucks it was going to sell because flushing and valve-turning work left crews short on vehicles — cheaper than renting at $2,000 per truck for six months.